[JANUARY 2021] ECOGARDEN PROJECT’S PROGRESS UPDATE
Ecogarden project’s progress in 2020 - Some highlights.
I. Legal
• Completion of legal component on investment.
II. Construction
• Complete 90% of the entire TT2 road, landscape culverts, landscape bridge No. 02, national school gate.
• Completion of 90% green landscape of Square, CC02 Lake Park, route TT2, East West Lake.
• Camellia area: Completion of foundation of 93/171 units.
III. Some of the latest images of the project:
• Completion of legal component on investment.
II. Construction
• Complete 90% of the entire TT2 road, landscape culverts, landscape bridge No. 02, national school gate.
• Completion of 90% green landscape of Square, CC02 Lake Park, route TT2, East West Lake.
• Camellia area: Completion of foundation of 93/171 units.
III. Some of the latest images of the project: